Machine Positioning of No. 3 coke Plant of Esfahan Steel Company

EPC Basis
Project Description: Design, Procurement, Developing of Control & Monitoring System Software, Installation and Commissioning of Control System (EIA) for Machine Positioning of No. 3 coke Plant in TAVAZON Project of ESCO including: - Coke Pusher Machine - Quenching Machine - Transfer Machine - Charging Car based on S7-400H Siemens PLCs & PCS7 software (Approx. I/O No.: 1200, Capacity: 900,000 ton/year
Duration: 2 Years
Starting Year: 2014
Location:Esfahan
 

0%



Modernization of Galvanized Coil and Sheet unit of Amirkabir Steel Co.

EPC Basis
Project Description: Design, Procurement, Developing of Control & Monitoring System Software, Installation and Commissioning of Control System for SSL unit of Amirkabir Steel Co.
Duration: 6 Months
Starting Year: 2016
Location: Kashan, Esfahan
 

0%



Modernization of Material Storage, Stacker & Reclaimer of Esfahan Steel Co

EPC Basis
Project Description: Design, Procurement, Developing of Control & Monitoring System Software, Installation and Commissioning of Control System (EIA) for Modernization and Expansion of Raw Material Storage and Stacker & Reclaimer Machines of ESCO, one of the biggest in the middle east material handling project
Duration: 3 Years
Starting Year: 2011
Location: Esfahan
 

0%



Raw Material Handling of ESCO

EC Basis
Project Description: Project Description: Design, Procurement, Developing of Control & Monitoring System Software, Installation and Commissioning of Control System (EIA) for Raw Material Handling of Esfahan Steel Company.
Duration: 3 Years
Starting Year: 2011
Location: Esfahan
 

0%



Melt Shop Plant of ESCO

E Basis
Project Description: Project Description: Upgrading and modifying Software from PCS7 Version 5.2 to PCS7 Version 7.1 .
Duration: 18 months
Starting Year: 2012
Location: Esfahan
 

0%



Low hydrogen annealing of Mobarakeh Steel Company

EC Basis
Project Description: Design, Procurement, Developing of Control & Monitoring System Software, Installation and Commissioning of Low hydrogen annealing of Mobarakeh Steel Company based on Siemens PLCs & PCS7 software *(Approx. I/O No.: 2000)
Duration: 18 Months
Starting Year: 2015
Location: Esfahan
 

0%



Heat Up Procedure of No.1 Battery in Esfahan Steel Company

EC Basis
Project Description: Design & Developing of Monitoring System Software for Heat Up Procedure of No.1 Battery in ESCO, based on ADAM Modules & WINCC HMI software (Approx. Thermocouple No.: 400)
Duration: 6 Months
Starting Year: 2014
Location: Esfahan
 

0%